Project Management: Example on Calculating Break Even Point
Your firm designs training materials for computer training classes, and you have just received a request to bid on a contract to produce a complete set of training manuals for an 8-session class. From previous experience, you know that your firm follows an 85% learning rate. For this contract, it appears that the effort will be substantial, running 50 hours for the first session. Your firm bills at the rate of $110/hour and the overhead is expected to run a fixed $600 per session. The customer will pay you a flat fixed rate per session (Per Session Price.) If your profit markup is 20%, what will be the Total Price, the Per Session Price, and at what session will you break even?
0
(0 Ratings)
a. What is the Total Price?
This is what you would charge the customer so that you can have your profit markup of 20% over all of your costs. To calculate this, first figure out your cost per each session, add them up, and then add your profit.
Total Price = C18+(C18*B6)
= $34,479.22 + ($34,479.22 x 0.2)
= $41,375.07
b. What is the Per Session Price?
This is the revenue that the customer pays you each time you complete a session. It is calculated by dividing the Total Price by the number of sessions.
= $41,375.07 / 8
= $5,171.88
c. What is the Break Even Point?
At the beginning, your cost per session is more than your revenue per session. Gradually, your cumulative revenue matches the cumulative cost, and eventually exceeds it so that you can end up with the desired profit. The break-even point is the session at which, for the first time, your revenue exceeds your cost. Once you have the cost and the revenue per session, you need to calculate the cumulative cost and cumulative revenue. Then find the session when the cumulative revenue exceeds the cumulative cost for the first time. That will be the breaking point.
Break-even point is where Cumulative Revenue > Cumulative Cost
It is Session 3 where; $14,914.57 (Cumulative Cost) is less than $15,515.65 (Cumulative Revenue)
In this thought-provoking response, the author's perspective is skillfully backed by an extensive body of comprehensive research and readily available information, offering a well-informed and compelling exploration of the subject matter.
Questions Related to Project Schedule, Cost, and Resource Management
|
A manufacturing firm has set up a project for developing a new machine for one of its production lines. The most likely estimated cost of the project itself is $1 million, but the most optimistic estimate is $900,000 while the pessimists predict a project cost of $1,200,000. The real problem is that even if the project costs are within those limits, if the project itself plus its implementation cost exceed 1,425,000, the project will not meet the firm’s NPV hurdle....
1) List 5 Advantages and 5 Disadvantages of Matrix Project Organization. 2) Discuss how your management style might differ in a matrixed organization from the management style you might use in a project-oriented organization.
Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. ...
The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.
A project has just completed its 87th item in the project plan. It was scheduled to have spent $300,000 at this point in the plan, but has actually spent only $250,000. The project manager estimates that the value of the work actually finished is nearly $200,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the Critical Ratio?
A project in its 26th week has an actual cost of $300,000. It was scheduled to have completed $325,000 worth of work at that point in the project. For the work performed to date, the budgeted value is $350,000. The project has a total budget of $500,000. What are the cost and schedule variances for the project? What are the SPI and CPI? Assuming that both schedule and cost variances will affect the remaining work, what is the EAC?